BLOG: MDEQ Crumb Rubber Modified Asphalt Projects


2014 Bennett Road Leveling Course Construction Photos

Photos taken on August 25th, 2014


2014 Benett Road

Bennett road 3E1 leveling course was constucted on Monday, August 25th, 2014. About 700 tons of 3E1 CR-HRC was placed on the eastbound lanes of Bennett road. Construction started at the Okemos Rd./Bennett road intersection. Same day, 3E1 HRC (Control) was also placed on the westbond lanes.


3E1 CR-HRC, eastbound lane, ~2300ft.

Leveling Course Plan (Click image below to see the pdf)


Top Course Plan (Click image below to see the pdf)