Wednesday, April 25th Finished connections and soldering for connections between voltage monitoring system. Tested system on arduino. |
|
 |
Friday, April 20th Tested GSM functionality between devices. Tested ethernet monitoring system. Added connections between devices and tested accurate measuring of digital pin between modules. |
|
 |
Thursday, April 12th Finished design of all prototypes. Tested functionality of each module independently.
|
 |
Friday, March 16th Finalized parts list. All parts ordered.
|
 |
Wednesday, March 7th Final approval for project objectives from sponsor.
|
|
|