HISTORY
Contamination in the Unit C3 Aquifer was discovered in late 1985. Between
the years of 1987 and 1994 GSI used a single water supply well located
near the property to extract 15,000 lbs of 1,4-dioxane. The contaminated
water was injected back into the ground untreated through a deep injection
well. The well was installed to nearly one mile deep. It had been originally
intended for the discharge of wastewater under a permit issued by U.S.EPA
in 1981. In 1994 GSI did not renew the permit due to the maintenance and
operating costs of the well. Not renewing the permit halted the operation
of 1,4,-dioxane extraction from the aquifer. From 1994 to 1997 the contamination
continued to migrate with the groundwater away from the GSI property.
Prior to the closure of the reinjection well in 1994, GSI proposed a work
plan using surface water discharge to the Remediation and Redevelopment
Division (RRD). The work plan was approved but due to accommodate local
concerns it was never implemented. Instead a second work plan was submitted
to the RRD in 1995. This work plan proposes, if feasible, groundwater
reinjection. However, expected difficulties with reinjection and the inability
to guarantee that the reinjection would not cause further movement of
the contamination ruled out any feasibility of reinjection.
LOCATION
The Core Area is defined as the area of the Unit C3 aquifer that is contaminated
with 1,4-dioxane exceeding 500 ppb. A portion of the PLS property is situated
above the Core Area. The Unit C3 Aquifer is connected to the deeper channelized
D2 aquifer which flows northeast to the Evergreen System. The Core Area
is also the source of contamination in the Unit E aquifer.
SYSTEM STATUS
There is a total of six extraction wells in the Core Area. These extraction
wells are removing about 340 gallons per minute of contaminated groundwater,
the water is then treated and released to the Honey Creek Tributary. Remediation
of the Core Area is planned to continue until generic cleanup criterion
is achieved. Continued monitoring of the site will occur for ten years
following the achievement of the cleanup criterion.