|
Current Status of Project
U.S. EPA approved the RFI Work Plan in March 2002 and Envirosafe Services
of Ohio, Inc., has begun its implementation at the ESOI property. ESOI
contracted with BEC Laboratories, Mannik and Smith Group, TolTest, Terra
Probe Environmental, ENVIRON, and Bison Geophysical Services for the work
at the site. Phase I work began March 21 and, as of August 31, was about
80% complete. This phase is primarily concerned with placing monitoring
wells, conducting soil borings, and preliminary identification of the
ex-tent of contamination at the site. The full extent of contamination
will be investigated during Phase II of the RFI. Validated laboratory
data are not yet available. Complicating the beginning of work was a March
10 diesel fuel tanker truck accident that resulted in a large oil spill
(1,200-1,500 gallons) along the north property line near SWMU 5 along
Millard Road. The responsible party for the diesel spill conducted a cleanup
under the direction of Ohio EPA’s Division of Emergency and Remedial
Response. Therefore, at this time the effect of the diesel spill on the
investigation of SWMU 5 is unknown. The effects will not be known until
samples are received.
The following monitoring activities have occurred, as reported in monthly
updates provided by ESOI to EPA Region 5.
-
Bison conducted resistivity testing at SWMUs 5, 6, 7, 8, 9 and 10.
(Resistivity testing is a method of subsurface detection that measures
changes in conductivity by passing electrical current through ground
soils.)
-
Soil borings were taken at the following SWMUs:
o North Sanitary Landfill, SWMU 6,
o Central Sanitary Landfill, SWMU 7,
o Millard Road Landfill, SWMU 5,
o Old Oil Pond, SWMU 8,
o and New Oil Pond, SWMU 9.
o Samples were submitted from all except SWMU 9 due to the absence
of liquid in #9.
-
Monitoring wells were placed around SWMU’s 5, 6, 7, 8 and
9, Cell F (SWMU 1), and the Ash Disposal site (SWMU10).
-
Two permanent shallow groundwater wells were placed in the contact
zone between the lacustrine soils and the upper till. These wells
are called H-7S and H-8S.
-
There was no leachate sampling conducted at closed cells G, H, and
I, consistent with the RFI. Those cells were closed in accordance
with RCRA regulations and have RCRA permitted caps. Visual inspections
confirmed the stability of the cells.
-
In May, a dye test of the Building C floor drains was completed;
results demonstrate that all drains flow to the sanitary holding tanks.
-
A background monitoring well cluster was installed East of Cell M
at the soil stockpile property.
-
Borings and temporary wells around SWMUs 6 & 7 were installed.
-
Competent bedrock was encountered at a depth of 87 feet at the background
monitoring well nest location. (“Competent bedrock” refers
to bedrock with less fracturing and higher resistivity. Competent
bedrock tends to be less permeable and less prone to allowing contaminant
migration.)
-
Soil samples found soil cover thickness ranging from 2 feet to 22
feet over various cells.
-
Surface water samples for analyses of volatile organic compounds,
semivolatile organic compounds, polychlorinated biphenyls, inorganic
analytes, pesticides, and herbicides were collected from Otter Creek.
Alterations to the original RFI sampling locations were made due to gravel
and debris in the sediment sampling locations; many changes were at the
request of the U.S. EPA.
-
At sampling locations 1, 3 and 9, sediment samples were collected
from 15-25 feet from the surface water sampling locations due to gravel
or sand at the surface water sample locations.
-
Sampling location 5 was moved due to an oil like material observed.
This area is adjacent to the Sun Pipeline facility and the oil like
material may originate from that facility.
The revised boring plan was submitted to the EPA on August 9, 2002. Some
of the changes included:
-
Multiple step out borings (borings installed further out from sources
of contamination to determine extent of contamination) were conducted
and the number of temporary groundwater monitoring points was reduced
due to a lack of discernible soil boundaries between SWMUs 7 and 6,
and SWMUs 7 and 9.
-
Soil borings and temporary monitoring wells were installed due to
topography and waste in S1-U/L (Cell F) and S6-U/L (Northern Sanitary
Landfill).
-
In SWMU 7, 2 wells were moved east of the interior access road (west
of Cell H) due to topography and waste.
-
Only 1 well was placed between the Northern Sanitary Landfill and
the Central Sanitary Landfill due to waste.
-
Only 1 temporary well nest was placed between the Central Sanitary
Landfill and Cell G due to waste.
-
SMU 9 has no wells due to waste.
-
2 wells for SWMU 5 were moved north and south due to waste.
-
A petroleum odor on the outside limits of the waste between Millard
Road (#5) and Otter Creek was detected. Temporary ground water monitoring
points were installed and soil samples collected by ESOI and OEPA.
Other activities of note include:
-
An ecological assessment and habitat characterization was done. A
Blandings turtle and coyote were seen.
-
EPA was on site (through contractors Booz Allen) July 24 through
July 26 to monitor the activities.
-
The Bison geophysical report was completed in August. The report
summarizes geological and physical features of the ESOI property.
-
Several geotechnical samples (soil and other geological materials)
did not maintain their integrity (they fell apart) on extrusion from
Shelby tube samplers. (Shelby tube samplers are designed to take undisturbed
samples in cohesive type soils and clays.) ESOI is evaluating whether
those samples should be collected again.
Other sections of the TOSC Outreach Plan:
|