What's Due, and When...  Spring, 2007

1. Professional Self Assessment Report -- Due Wednesday, April 18, to facilitator (one per student). Format and contents described on web page.

2. Final Demonstration for facilitator,  sometime BEFORE ECE Design Day, Friday, April 27, in the lab, OR at ECE Design Day in MSU Union on April 27, if your project can be demonstrated completely there.

Two copies of your poster prepared according to specifications and  posted on the course web page.  Team members, in staggered shifts, must be on hand 8:00am – 1:30pm in Parlor C, MSU Union, except when team is making its Final Oral Presentation (see schedule on web page or in program).  Each student must also attend a minimum of two other oral presentations, providing written feedback about the presentations.  Each student must also fill out and hand in (in special boxes at Design Day presentation rooms) an evaluation form regarding the contributions of their fellow team members.

3. Final Written Report (one report per team)- Prepare seven PRINTED copies (three “normal” and four “special”) -- for Instructor and Facilitator and Sponsor.  Send electronic copies to Goodman and Facilitator, and turn in printed copies in ECE Office, marked clearly as to who each copy is for.  The four special copies are for judges (marked “JUDGE’s COPY” on the front), and are the SAME as the “normal” copies UNLESS the team is operating under a confidential disclosure agreement.  In that case, the four copies must have all confidential material REMOVED (including detailed schematics, code, and anything else now considered confidential and not to be talked about on your poster or presentation).  Where you have removed something, insert a note “CONFIDENTIAL MATERIAL REMOVED” so the judges will know that something confidential was there in the actual final report.  These copies go to the ECE OFFICE at the same time, to Goodman’s attention.  If some team member will need additional print quota to print these (and posters), email Goodman before noon Wednesday with the name and email address of the person to receive the page quota, and say how many pages (include poster quota, too).

Due – April 25, Wednesday, not later than 5:00pm.  Paper copies may be given to secretary in ECE Office to be put in Goodman's and facilitator's mailboxes, but NOT LATER than 5:00pm. Paper copy required to facilitator and to Goodman; also send electronic copy to goodman (goodman@egr.msu.edu), and post on your web page (and include on your CD).  [NOTE:  teams that have a confidential disclosure agreement with sponsor should NOT post their final reports on the web pages, but turn them in on paper and electronically to Goodman and on their CD, and to their facilitator.  Judges’ copy of Final Report:  If your team has a confidential disclosure agreement (CDA), you must print a version of report for judges with CONFIDENTIAL material (code, detailed schematics, PCB layouts, etc.) removed and MARKED as removed.  If no CDA, just print for Goodman the extra four copies of the full report.]  A copy of the final report and CD must be prepared for the sponsor and either hand-delivered to them at Design Day or mailed to them (through the ECE Shop or ECE Office) no later than Monday, April 30.  Unless you are notified otherwise, you must also deliver/ship your prototype to the sponsor by Monday, April 30, or give it to them at the end of Design Day.

Final Report Format

Main Body of the Report

Executive Summary

Design Objectives/Product Description

                Include FAST diagram with discussion of how you addressed the defined functions in

                your design (building on the function analysis homework assignment your team did).

Design Specification -- Should match that given in your proposal

Final Design Implementation

                You should also include various options considered and why you chose your final design

                You should also discuss simulation results you obtained here

Final Design Performance

                Evaluate with respect to the design specification

Summary of Design Team Organization and Roles

Summarize the Key Intellectual Contributions Each Member of Your Team Made to this Project

Discussion and Suggestions for Future Improvements

Conclusions

Complete List of References Used During the Semester for your Project

Appendices

Include all schematics and parts lists (create good drawings)

Include models and simulation results (e.g. SPICE simulations if done, etc.)

Include software code listings

Include PCB board layout plots

Include specification sheets of specialized parts (limit the number of pages- maybe just put key pages)

Include any other information that documents your product

4. Final Oral Presentation (one per team)-(Friday, April 27, 8am – 11:40am; at Design Day, MSU Union, according to posted schedule.

Length 25 minutes – 15-16 minutes for presentation, 9 minutes for setup/answering questions from judges, demonstrating for judges

PowerPoint presentation

Organization

Describe your project goals and team organization

Review your design specifications

Show the final design and evaluate it with respect to your proposed design specifications

Offer suggestions for future design improvements

NOTE: Each student is required to attend session (s)he presents in, plus at least two other talks.

5. Final CD ROMs (two per team -- one for instructor, one for sponsor) -- Goodman's copy with his printed final report, due Friday, April 27, 4:30pm; you must hand-deliver other copy to your sponsor, together with anything else you are to give to sponsor, or you may package and address it for mailing and turn it in to the ECE Shop, not later than Monday, April 30, 2007, before or while turning in your other materials to the ECE Shop.)

Place a copy of your web page and all design team work (software, reports, etc.) on the CD ROMs. This is needed for the department’s ABET accreditation process, to document your work.

You can write the CD ROMs in the lab. Include a contents file on your CD ROMs.

Here is how you do that....

1. Contents file creation and verification:

rm contents.txt (to remove existing file)

ls -laR > contents.txt

du >> contents.txt (these two steps create the contents.txt)

chmod 775 contents.txt (change permissions on the newly created file)

2. CHECK THE CONTENTS.TXT FILE BY OPENING IT IN WORD AND VERIFYING IT

(PERMISSIONS AND GROUP (4TH COLUMN TO THE LEFT OF FILE-SIZE))

3. CHECK ALL FILE PERMISSIONS OF THE FILES ON THE CD ROM. CHANGE AS NEEDED. REMEMBER: IT NEEDS TO BE READABLE TO BE GRADED.

6. Hand In Your Project Notebook/Journal for the Last Time, ONLY to your Facilitator (mailbox).

Due 4:30pm, Friday, April 27, 2007, to Facilitator mailboxes (ECE Office will have a box where they can be turned in)

·  If you want to keep your notebook, you may copy and hand in your notebook entries since the last hand-in date – otherwise, just hand in the notebook.   If your team has signed an agreement assigning intellectual property to the sponsor, your notebooks will be given to the sponsor.

7. The completed web page including your oral presentations, proposal, progress reports, and final presentation (one per team) -- Due Friday, April 27, 2007, at 4:30pm, posted and on the CD-ROM. [Note:  do NOT post if your project is operating under a non-disclosure agreement.)

8. Your prototype is probably owed to your sponsor, and otherwise, it MUST be turned in to the ECE Shop.  If not sure which, check with Goodman.  If due to sponsor, you may deliver prototype (and CD-ROM) on Friday, if sponsor attends presentation; otherwise, you must package it for mailing and take it to ECE Shop no later than Monday, April 30, 2007, and they will send it to sponsor.

9. Complete and hand in your team’s Lab Equipment Return Form

It Must be Signed by the ECE Shop -- (one per design team take it there).  They will sign it when you have cleaned out your locker, turned in your lock, and returned all hardware furnished by ECE for construction of your project (except what will be given to your sponsor), for example, power supplies, specialized lab instruments, etc. ALL sponsors this semester should receive the prototypes you have built, plus any supporting material promised to them.

Due: Wednesday, May 2, noon, signed form in Goodman's mailbox (ECE Office).

The form is provided on the next page for you to print out, if lost.

4:30pm Friday, April 27, is the final due date for all ECE 480 deliverables except the Lab Equipment Return Form. Missing items will impact the evaluations/grades given, as will late items. 


ECE 480 Design Team Equipment Return Form-One per Team

(To be signed by ECE Shop, then returned to Goodman)

All items that you borrowed from the ECE shop, or had purchased through the ECE shop, and your team’s padlock must be returned to the ECE shop by noon on Wednesday, May 2, 2007. You also need to have all of your personal belongings out of the ECE 480 lab by noon on Wednesday, May 2, at which time the door will be locked.

 DESIGN TEAM #____________

Items below to be completed by the ECE shop staff:

Padlock returned:                                                                                                         YES NO

 

All equipment and tools borrowed from the shop have been returned:                YES NO

 

All parts obtained from or purchased through the ECE shop and NOT to be given to sponsor have been returned:             YES NO

 

Prototype has been packed for shipment to sponsor and taken to ECE Shop, or has already been delivered to sponsor.

 

The ECE Shop is satisfied that all items have been returned properly

                                                                        ECE Shop Signature__________________________

                                                                                                Date_____________________

 

Return completed form to Dr. Goodman no later than Wednesday, May 2, 2007.