Progress
|
Date:  5-1-2009 Design Day |
|
Date:  4-28-2009 Motion Sense Integrated |
|
Date:  4-28-2009 Power Hub Completed |
|
Date:  4-20-2009 GUI Completed |
| Building GUI |
| First Progress Report |
| Date:  2-20-2009 Final Proposal Submitted |
| Date:  2-18-2009 Pre-Proposal Presentation |
| Date:  2-16-2009 Angstrom OS Installed and Running |
| Date:  2-06-2009 Pre-Proposal Submitted |
| Date:  1-26-2009 First Phone Conference with Sponsor |